Stage Production Specifications

Stage Information

Stage Measurements

Calculated from the centerline of the stage and/or the upstage edge of the smoke pocket – 0', 0".

Proscenium Stage

  • Height of proscenium opening to fixed valance: 24'-9"
  • Width of proscenium opening to edge of plaster: 54'-8"
  • Deck to the walking surface of the grid: 70'-0"
  • Upstage edge smoke pocket to back wall: 37'-2"
  • Upstage edge smoke pocket to front of apron at center: 4'-9"
  • Upstage edge smoke pocket to front of apron at proscenium: 4'-9"
  • Upstage edge smoke pocket to house curtain pipe: 1'-4"
  • Upstage edge smoke pocket to 1st avail working set of lines: 2'-0"
  • Upstage edge smoke pocket to last avail working set of lines: 36'-0"
  • Center line to stage left wall, unobstructed: 47'-4"
  • Stage left wing space off-stage from proscenium: 20’-0”
  • Center line to stage right fly rail: 52'-5"
  • Stage right wing space off-stage from proscenium: 25’-1”
  • Stage right fly rail vertical clearance: +32'-9" (Mid-level Loading Gallery & Pinrail platform edge at +32'-9" starting at 42'-0" SR of centerline.)

Other Measurements

  • Road mix position: 10' x 22'-6"
  • Located 15'-3" to 37'-9" house-right of the house centerline.
  • 117' from fire curtain line to the near edge of the mix position.
  • Lighting control booth windows to fire curtain line: 149'
  • Spot booth window to fire curtain line: 175'
  • C-vom projector position to fire curtain line: 93'
  • Balcony edge projector position to fire curtain line: 118’

Line-Sets

  • Counterweight system/single purchase
  • 11,000 lbs. counter weight
  • 48 available sets
  • 5 lines per set/70' house pipes
  • High trim of house pipes +62'-6” from deck
  • 104 upright loft blocks provided for 52 spot lines. 5/8" UltraStrong ®, 3 strand twisted lay rope.
  • 1 block & falls
  • Pin rail located stage right Mid-Level Gallery at + 32'-9"
  • House battens are 2” schedule 40 pipe or 12” aluminum ladder truss

House Curtain

Gold buillotine and gold legs on a traveler track

  • Operated stage right deck, not at Locking Rail.

Orchestra Pit

  • Front of orchestra pit to apron at centerline 13'-0"
  • Front of orchestra pit to apron at off-stage edge 6'-6"
  • Orchestra pit extension under apron at center 0'-0"
  • Orchestra pit side to side at apron 50'-4"
  • Adjustable hydraulic pit
  • Curved railing

Load In/Out

South Dock / USL

  • One (1) truck loading dock. (Push distance between stage and dock is flat and level, approximately 16'.)
  • Door is 6’-8” W x 9’-5” H
  • Freight elevator to basement – 5’-9” x 5’-3” with 1000 lbs. max load, no passengers allowed.
  • Forklift not possible on the south dock or stage. Forklift in street possible, but not available unless ordered in advance.

North Dock / USC

  • Two (2) truck loading dock (Push distance between stage and dock is approximately 100'.)
  • Doors are 8’-7” W x 13’-4” H
  • Small forklift available in-house for stacking/un-stacking. North loading dock area only.